Wednesday, March 30, 2011

WIP- Part IV

Today, we finally met our next door neighbor ~ Alison and Laura (Laura told me Alison is her girlfriend). I was guessing, they might be couple! Anyhow, we had met our neighbor....


The main reason of this blog is to continuing showing you the progress of my house
On 28 Mar 2011 Internal bricklayer (red one) just started
Entrance door

Another layer of the brick


30 Mar 2011 Internal bricklayer (red one) was partially completed (waiting for the rooms)

Wednesday, March 23, 2011

WIP- Part III

Stage 3: Bricklayer
(The pic was taken on 22 Mar 2011)

Black frame(from left to right): Room 2, Toilet, Bathroom 
White frame: Door from garage to laundry

 










Black frame: Sliding door to Alfresco

 View from Alfresco 

Sunday, March 20, 2011

???

Listening to Malaysia Mix FM 
"Cold Play- Viva La Vida" is on-air now at 9.46 on this beautiful Sunday 20 Mar 2011

Housemates (and definitely my sis) are still sleeping...
Husband is on the way for badminton match....
Mum must be eating her breakfast or lying on the bed enjoying her series of novel...
Fellow colleagues are taking calls
Me? Blogging (of course!)

What about you? Cooking? Washing? Babies?...
No matter how is it, certainly it must be an enjoying day to YOU n ME!


---------@@@@@----------

I could track the progress of the construction of my new house:
(one in blue=completed)

---------@@@@@----------

Anything happy thing to share- I'm going on a short break again during Easter! We're heading to Margaret River (about 3hours drive from Perth)- Another B&B (Bed & Breakfast) at AUD90/day at Brilea cottage(family owned). Supposedly, the min stay of every hotel, resort,chalet is 3-days during peak holiday (Easter and Xmas) . Luckily, the owner allow us for just 2-days (as I told you-I'm a contract (no leave entitled). Even just 3-days, I have to apply for leave. Anyhow, that's not important at all as long as the journey benefited me! Hahaha....


Friday, March 11, 2011

Friday Morning

It's now 6.43am and I'm not working!
The weather is about 28-29 degree- Cool and nice outside!

Today, I'll spend my time....
- Continuing my TVB series of course (Anyway, I've finished 'The Little Nyonya')
- 煲凉茶! (WIP)
- Waiting for husband to finish work at 1pm
- Visiting the construction site
- Accompanying husband for a hair cut
- Grocery shopping

It's now 7.27am....and I'm knocking off now..

Before I left, something to share you after my working hour at 8.15pm. Guess what? A nut pee in front of me and others in the train some-more! I could describe in just a word- GROSS! GOD, what happen to the world? (Luckily, he didn't show his X)

Wednesday, March 9, 2011

Hi Hi

Just drop by to say Hi before going to work!
Ya, I'm starting at 4.45~9.45 (5 hours shift)
That's the reason I'm still here, blogging! :)
(FYI, I'm in the office, taking calls now)

Recently, I'm watching a Singapore drama- The Little Nyonya '小娘惹'. This drama reflected the life of  a nyonya with tears and laughter..I'm just half way through.. Still lots more to go. Perhaps, let me briefly introduce you the drama

Title:  The Little Nyonya '小娘惹'
Episode: 34
Staring: Jeanette Aw 欧萱, Pierre P'ng 方展发, Xiang Yun 向云, Felicia Chin 陈靓萱
Synopsis:  A life of a maid in Huang family, becoming a second mistress and 'torturing' life continued....


Anyone watching?

Thursday, March 3, 2011

WIP- Part II

I have new neighbor!

FYI, my next-door neighbor started their construction a week earlier than us. Unfortunately, we still have no chance meeting the owner yet (my neighbor). We used to visit the site when we're free (is about 5 -8mins from our current location). We did notice that there are a few more construction to be going on, however, till now still they haven't start yet !(Awaiting building license,perhaps?) At this stage, only the two of us commencing the construction...

I received a letter from our builder that we need to attend 4 meetings during the construction:
- Brickwork Meeting
- Ceramic Tiler Meeting
- First Practical Completion Inspection
- Final Completion Inspection 
 
Hopefully, we could move in before summer. Normally, it took about 6-months to complete the construction! From the estimation time length, it should be in August 2011. We could take a month for preparation (e.g. painting, flower/ grass planting and etc) as August is "Ghost Festival" (July in Chinese calendar). Anyway, we will see how it goes. Perhaps, it might complete sooner. Who KNOWS?

In the meantime, of course, I will definitely calculating/budgeting for the new house (surveying for furniture and electrical appliance) I did show this to Angie. Maybe I should share it with you too!


Before that, I have been visiting shops (IKEA and other furniture shops) but can't really find the ONE. Therefore, I decided to check out from ebay website and finally I saw this! The problem is now I have no place to keep it (currently, I'm just renting a room!) I wish they could keep that in their depot until my house is ready. Unfortunately, they are only able to keep that for a month. I'm thinking of renting a small container- still awaiting their reply :)

What do you think of?

Wednesday, March 2, 2011

WIP-Part I

Stage 1: Earthwork


Stage 2: Slab